Tüpraş Rafinery - New Substation and Service Building, Civil Works
Partial engineering, construction for civil works related to the construction of a New Substation and Service Building.
Locations: Kırıkkale / Turkey
Start: 2023 - (ongoing)
Planned Completion Date: Q3/2024
Client: Tüpraş
Main Contractor: Tekfen
Tüpraş, with its four refineries located in İzmit, İzmir, Kırıkkale and Batman, has an annual total processing capacity of 30 million tons of crude oil. Besides being Turkey's largest industrial company and a leading player in the energy sector, Tüpraş is also positioned as the 7th largest refinery company in Europe and one of the most complex refineries in the Mediterranean basin. The scope of work concerns the execution of partial engineering, construction and erection of civil works.
Activity Basis Scope of Supply:
- Partial Engineering
- Construction
Scope of Supply:
- Reinforced Concrete: 1938.9 m³
- Steel Re-Bar: 233.6 tons
- Formwork: 8536.6 m²
- CMU Wall (200 mm): 1136 m²
- Brick Wall (200 mm): 209 m²
- Rockwool Thermal Insulation: 1653 m²